By Natalie Barszcz
At the Triview Metropolitan District (TMD) meeting on April 20, the four-member board heard about the Northern Delivery System (NDS) pipeline project timeline, approved the fourth amendment to a contract and an infrastructure agreement, and held an executive session to discuss negotiations regarding multiple projects, acquisitions, and negotiations.
Northern Delivery System
District Manager James McGrady said the kick-off meeting for the NDS project had taken place earlier in the day and construction would begin as early as late April with clearing the path of the pipeline. The pipeline installation is expected to begin by mid-May, beginning with the installation from “B” plant to “C” plant, then behind Sanctuary Pointe to Baptist Road. The pipeline installation along Roller Coaster Road is expected to last two months and begin on July 1. The roads will not be closed but at times will be restricted to local traffic only. All the pipeline is expected to be installed by October to allow a full asphalt overlay of the paved roads before winter. The pump station construction is expected to begin mid-June/July, he said.
NDS project hotline
Residents can keep up to date with the project timeline and submit comments and questions at www.triviewnds.com or leave a recorded message at 719-799-6533. Kiewit Infrastructure Corp., the main construction company and project manager, will be addressing the public’s concerns during the project. Residents can also access the project site via www.triviewmetro.com.
Kiewit contract amendment
McGrady requested the board review and approve the fourth amendment to the contract between Kiewit and TMD, for a maximum price of about $2.9 million for the construction portion of the Booster Pump Station. The complete Booster Pump Station will cost about $5 million. Last month, the third amendment approved the purchase of materials for the station that will be constructed on Colorado Springs Utilities property. The water will be pumped from the pump station to “C” Plant at about 260-270 psi. The high-pressure valves and surge tanks drove the cost a little higher, he said. See www.ocn.me/v23n4.htm#tvmd.
Th board unanimously approved the fourth amendment.
McGrady said the total cost of the NDS project is about $21.8 million, about 10% higher than originally estimated in 2022.
Colorado Springs Utilities contract
McGrady said the Colorado Springs Utilities (CSU) convey, treat, and deliver contract was approved at the Colorado Springs City Council on March 28.
Note: The 25-year contract with CSU to convey, treat and deliver district-owned water to TMD residents will cost about $1.6 million in the first year.
Home Place Ranch infrastructure agreement
McGrady requested the board consider approving the first amendment to the Home Place Ranch Water and Sewer Infrastructure agreement between Home Place Ranch LLC and TMD. The development has shrunk from the original plan of about 1,000 homes to the new plan of about 300-400 homes, he said.
Water attorney Chris Cummins said when Challenger Homes purchased the property in 2018, the agreements were clunky for both parties. The infrastructure agreement was revised in 2019 when the district thought the developer would build about 400-600 homes. Since then, the developer has realized the hundred-acre woods, the topography, and the Preble’s meadow jumping mouse habitat would be difficult to develop, and further reduced build-out. It is a good agreement that confirms the number of homes and provides a schedule, he said.
McGrady said the agreement had been available for some time, and the district has received $600,000 for the sewer service from the developer. The development is 600 homes less than originally proposed about 20 years ago, but a significant number of homes have been built, with the developer paying for the infrastructure. Nothing has changed except the developer is ready to sign the agreement, he said.
The board unanimously approved the agreement.
Upper Monument Creek Waste Water Regional Treatment Facility
District attorney George Rowley requested the board approve Resolution 2023-03, appointing McGrady as the district representative for the Upper Monument Creek Waste Water Regional Treatment Facility (UMCWWRTF). Each of the three co-owners of the facility nominate a representative, he said.
The board unanimously approved the appointment.
Financial report
The board reviewed and approved checks above $5,000, and unanimously approved the financial report as presented for March.
Note: The next district newsletter is expected to be sent to residents at the end of May. For more information on the district’s water sources, residential watering restrictions, and district projects, visit www.triviewmetro.com.
Utilities Department update
Superintendent Shawn Sexton said the following:
- The Arapahoe 4 Well will be going online in late April, and the Arapahoe 9 Well will be out of service while the Dawson 9 is off-line until a new motor is received. A9 is really in service but needs to run with D9 until it can be disconnected from it.
- The plant is keeping up with demand without full utilization of the online wells.
- A Plant is running 24/7 and B Plant is running about 12 hours a day. TMD has a large capacity of water in reserve.
- The booster pump station at C Plant on Vanderhoof Court had a pump upgrade on the No. 2 booster pump, but programming issues exist that will be completed April 24.
- Filters 1-2 were placed back into service at B Plant after Bacti clearance was completed. No damage had occurred to the filters after 20 years of service.
- Sewer line TV camera work was completed at Homeplace Ranch.
- Staff completed a walk-through with Nick Harris of JDS Hydro (a division of RESPEC), for five tie-ins between C and B plants for the NDS pipeline project. The project is large and will require coordination between the contractors and the TMD staff.
Forest Lakes Metropolitan District update
Sexton said TMD is coordinating with construction crews at the Forest Lakes Metropolitan District (FLMD) plant. FLMD construction crews are installing new raw water lines and making improvements to the well field for the ground water plant in the Falcon Commerce Center. TMD staff will be coordinating with the crews, he said.
Director James Otis asked about the Variable Frequency Drive (VFD) pump controller that failed during a recent snowstorm at the ground plant in FLMD.
Sexton said a short out occurred in the VFD unit cabinet, causing a failure that likely occurred due to a lack of ventilation as a result of snow buildup. A loaner unit was hooked up to run manually. The failure is not preventing access to any supply of water and the surface plant has been online since mid-April.
Otis questioned if any possible design flaws at the FLMD plant were causing failures, given the short age of the plant.
Sexton said it is not due to design flaws, just hours of run time causing wear and tear, and the unit was approaching end of life, but the snow did not help.
Public Works and Parks and Open Space update
Superintendent Matt Rayno said the following:
- The new barn in “A” yard is about 95% completed with the utilities stubbed out. The structure is awaiting trenching and a garage door, and the concrete floor is scheduled to be poured in late April. The yard will be graded and paved in mid-May. The heated barn will house the district’s sewer cleaning Vactor truck and snow removal vehicles and equipment. See www.ocn.me/v22n9.htm#tvmd.
- The crews are working on the trail system irrigation for May 1, and seeding is expected to begin mid-May.
- Spring cleanup around the district is underway.
- Treasurer/Secretary James Barnhart asked about the progress on Sanctuary Pointe Park after seeing dirt being moved.
Rayno said the original engineering plans had to be revised due to the 30-year floodplain requiring additions to the site. The contractor will be installing drainage and is hoping for a July 4 completion.
Note: The Sanctuary Pointe developer is responsible for the construction of this park.
Americans with Disabilities Act ramp installed
This reporter requested the reason for the Americans with Disabilities Act (ADA) compliant ramp that connects the slope at the cul-de-sac at the north end of Agate Creek Drive to the trail system and said three residents had raised multiple questions about a potential loss of view, wheelchairs negotiating the ramp, and skateboarders who had already been using the ramp.
Rayno said the installation of the ADA-compliant ramp that joins to the trail between Venison and Saber Creek Drive was not requested by homeowners; it was a district decision to enhance the area and include access from the cul-de-sac to the trail. The hillside was scrub grass, but it is now landscaped with boulders, maples, and crabapple trees, and the remainder of the feature will be landscaped and fill the void, he said.
McGrady said the slope was around 2% and a switchback was incorporated into the design to keep the path ADA compliant. It is part of the overall improvement of the area and there is nothing that will impede any view, he said.
President Mark Melville and Vice President Anthony Sexton did not feel that the ramp would be a problem drawing skateboarders, and bikers would just ride on through down to the trail.
Rayno said “good luck” to skateboarders negotiating the ramp once the area is completed. He confirmed that the connecting trail would be ADA compliant, and views will be no less impeded than before the installation. It will be quite beautiful when completed by the end of July, and a bench may be added in the future, he said.
Executive session
The board moved into executive session at 7:14 p.m. pursuant to Colorado Revised Statute 24-6-402(4) (a), (b), and (e), to discuss negotiations and receive legal advice associated with water delivery infrastructure, water acquisitions, and property acquisitions.
Steve Sheffield, assistant district manager, confirmed that when the board returned to the regular session there were no actions taken, and the meeting adjourned at 8:38 p.m.
**********
Meetings are usually held on the third Thursday every month at the district office at 16055 Old Forest Point, Suite 302. The next regular board meeting is scheduled for May 18 at 5:30 p.m. For meeting agendas, minutes, and updates, visit https://triview.com.
Natalie Barszcz can be reached at nataliebarszcz@ocn.me.
Other Triview Metropolitan District articles
- Triview Metropolitan District, Feb. 11 – Northern Monument Creek Interceptor pipeline project IGA approved (3/1/2025)
- Triview Metropolitan District, May 18 – Former directors recognized; new directors sworn in (2/22/2025)
- Triview Metropolitan District, Jan. 23 – 2025 water and wastewater rates and fees increase approved (2/1/2025)
- Triview Metropolitan District, June 22 – NDS pipeline project progressing (1/23/2025)
- Triview Metropolitan District, Dec. 16 – Study reveals water and wastewater rate increase; administrative/utility offices pursued (1/4/2025)
- Triview Metropolitan District, Nov. 21 – 2025 annual budget approved; mill levies set (12/5/2024)
- Triview Metropolitan District, Oct. 24 – Bond pursued for road widening project (11/2/2024)
- Triview Metropolitan District, Sept. 19 – Northern Delivery System fully operational; resident raises traffic concerns (10/5/2024)
- Triview Metropolitan District, Aug. 22 – 2023 budget amended; 2023 audit presented; district opposes initiatives 50 and 108 (9/7/2024)
- Triview Metropolitan District, July 18 – Northern Delivery System complete; land annexation approved (8/3/2024)