- Renewable municipal water supply increases
- Northern Delivery System update
- Public relations—the path to renewable water
- Operations report
- Financial report
- Executive session
By Natalie Barszcz
At the Triview Metropolitan District (TMD) meeting on Feb. 22, the board heard about an increase in the municipal renewable water supply and the tie-in of Colorado Springs Utilities (CSU) to the Northern Delivery System (NDS). The board also discussed informing the residents about the district’s path to becoming an 80% renewable water supply municipality and how sales tax and growth had helped achieve the district’s goal. The board held an executive session and approved the potential purchase of land.
Treasurer/Secretary James Barnhart and Director Amanda Carlton were excused.
Renewable municipal water supply increases
Water counsel Chris Cummins announced a successful water change case that decreed about 1,050 of the district’s water shares in the Fountain Mutual Irrigation Co. (FMIC). The decree changed the shares from agricultural water to municipal use water shares that equate to about 740 acre-feet in municipal water. The district leases 244 acre-feet of those shares to Fountain Valley Power for about $15,000 per month. The remaining acre-feet will increase the municipal water supply to the district by about a half a year’s worth of water from now on. In July that reusable renewable water will be available through the NDS, he said.
District Manager James McGrady said about 80% of the district’s annual water supply beginning Jan. 5, 2025, will come from a renewable source, and the remaining 20% will be sourced from the district’s Denver Basin groundwater wells. The renewable water supply will further increase as more water rights come into play, he said.
Northern Delivery System update
Assistant Manager Steve Sheffield said Kiewit had requested substantial completion and the two-year warranty period begins for the NDS pipeline on Jan. 31. The tie-in to CSU occurred on Feb. 5, but the district is anxious to get water moving through the pipeline to ensure the system is working 100% and can hold pressure. Kiewit recognizes that the pump station will not be complete until June and the pipeline will not be fully operational until mid-summer, he said.
Cummins said some pressure testing has occurred and the fire hydrants installed along the pipeline route held the correct pressure when tested with the static water in the pipeline.
McGrady said the pipeline should hold, but there is nothing like running the water through the pipeline to know for sure. The NDS pump station (located east of Highway 83 at Old Northgate Road) is moving along in its construction and is framed with roofing to begin on Feb. 26. The interior will be dry-walled by the end of the month and then the installation of the pumps will begin, he said.
Public relations—the path to renewable water
President Mark Melville requested future newsletters reflect a timeline story beginning in 2015 on the district’s path to its renewable water source.
Vice President Anthony Sexton requested the newsletter communicate all the reasons for the decisions the board makes. Many of the projects and the district’s achievements are made through sales tax and growth, and an explanation would be useful for the residents, he said.
Director Jason Gross said the district has a wonderful story of vision, good timing, smart decision-making and long-term thinking and it would be a tragedy to not capture and share with the residents as the district reaches the end of the tunnel on its path to renewable water sourcing for the community. The story sets a good example for other municipalities, he said.
Cummins said in the last seven years the board only had about three votes that were not unanimous, and it has been important to have a board that can listen, understand, and make sound decisions and allow the district staff and consultants to do the things they need to do based on those decisions.
McGrady said there has been no micromanagement from the board; it gave vision and direction, setting the tone for staff to follow then standing back with confidence as staff and counsel pursued the projects needed to sustain renewable water for the future.
Operations report
McGrady said the following:
- A meeting to discuss an emergency interconnect with the Town of Monument (TOM) was delayed due to scheduling conflicts and is now scheduled for March 4.
- The Bale and Arkansas Valley Irrigation Co. (AVIC) ditch change cases are both moving forward. The district is trying to avoid a trial on April 1 with the AVIC change case by getting the objectors out as quickly as possible.
- The re-vegetation plan for the AVIC in Buena Vista is in order, and that had been a problem for some objectors.
- The district is planning to build recharge ponds to accommodate the AVIC water in the future, after the change cases are decreed and the property is annexed into the town of Buena Vista.
- Northern Monument Creek Interceptor (NMCI) will kick off with a project meeting at the end of February.
- CSU held a meeting to discuss an indirect potable reuse plan. The district does not necessarily need the project to manage the district’s wastewater return flows unless it becomes more cost effective.
Sheffield said the following:
- D38, the TOM and the district have reached an agreement on the striping and layout on Creekside Drive. Two westbound lanes at Bear Creek Elementary School will be incorporated soon to assist with the drop-off/pick-up flow.
- TMD is exploring the possibility of widening Leather Chaps Drive and is working with Black Hills Energy to avoid the gas line that runs about 36 to 42 inches deep beside the road.
- Multiple meetings took place with the TOM planning staff and NES Inc. to discuss the water tank installation at Plant B on St. Lawrence Way in Promontory Pointe.
- An extensive meeting took place with Classic Homes to discuss a potential connection of sanitary sewer into the TMD collection system for Flying Horse North, Hodgen Road.
- District administrators are working with Ireland Stapleton Law to review and possibly revise the personnel manual.
Financial report
Sexton said he was curious about the check to Pikes Peak Regional Water Authority for $5,687.83.
McGrady said the annual Transit Loss Fee is variable and is required to pay for the re-calibration of the gauges on Fountain Creek down to the Arkansas River. Every water district that uses Fountain Creek for water transit pays the re-calibration fee annually.
Cummins said that the flows were excessive last year following the huge amount of rain received in May 2023.
The board accepted, 3-0, checks over $5,000 and the financial report for January as presented.
Executive session
The board moved into an executive session at 7:18 p.m. pursuant to Colorado Revised Statute 24-6-402(4) (a), (b), (e) to discuss acquisitions and receive legal advice for negotiations regarding water acquisitions, the Highway Users Tax Fund share return, strategic planning, and change cases.
Sheffield confirmed the board returned to the regular session at 9:20 p.m. In a 3-0 vote, the board authorized McGrady to sign a letter of intent to potentially purchase a 2-acre parcel of land near the northwest corner of I-25 and Baptist Road for the future home office and storage yard.
The meeting adjourned at 9:21 p.m.
**********
Meetings are usually held on the third Thursday of every month at the district office located at 16055 Old Forest Point, Suite 302. The next regular board meeting is scheduled for March 21 at 5:30 p.m. For meeting agendas, minutes, and updates, visit triviewmetro.com.
Natalie Barszcz can be reached at nataliebarszcz@ocn.me.
Other Triview Metropolitan District articles
- Triview Metropolitan District, Oct. 24 – Bond pursued for road widening project (11/2/2024)
- Triview Metropolitan District, Sept. 19 – Northern Delivery System fully operational; resident raises traffic concerns (10/5/2024)
- Triview Metropolitan District, Aug. 22 – 2023 budget amended; 2023 audit presented; district opposes initiatives 50 and 108 (9/7/2024)
- Triview Metropolitan District, July 18 – Northern Delivery System complete; land annexation approved (8/3/2024)
- Triview Metropolitan District, June 20 – Wastewater processing explored; legislative changes raise concern (7/6/2024)
- Triview Metropolitan District, May 23 – Water and wastewater rates and fees increase approved; billing discrepancy solves wastewater increase (6/1/2024)
- Triview Metropolitan District, April 25 – Water and wastewater fees/rates discussed; water rights lease agreement approved (5/4/2024)
- Triview Metropolitan District, March 20 – Additional acre-feet of water decreed; escrow agreement approved (4/6/2024)
- Triview Metropolitan District, Jan. 8 and 25 – Mill levy lowered; 2024 budget approved (2/3/2024)
- Triview Metropolitan District, Dec. 13 – 2024 budget public hearing presented; rate increases discussed (1/6/2024)