By James Howald
At its September meeting, the El Paso County Regional Loop Water Authority (EPCRLWA, or the Loop) board awarded a contract to design the expansion of the Calhan Reservoir. Corben Fromm, of Fromm and Co. LLC, reported on the Loop’s finances. Finally, the board decided to discontinue their monthly workshop meetings.
CDM Smith to design reservoir expansion
Patricia Hutchinson, a civil design engineer with Merrick and Co., who is acting as the Loop’s workflow manager and coordinating the work being done by the consulting and engineering companies contributing to the project, told the board that two companies had been interviewed on Oct. 10 for the role of designing the expansion of the Calhan Reservoir, where water diverted from Fountain Creek will be stored before being delivered to customers in the participating water districts. She recommended the board award the contract to CDM Smith, which had proposed to do the design work for $426,000. CDM Smith’s proposal included a geotechnical survey, she said.
Board President Jessie Shaffer moved to award the contract to CDM Smith, and the board voted unanimously in favor.
Financial matters
Fromm told the board that invoices totaling $199,000 had been received in September. The board approved paying the invoices.
In his financial statement, Fromm said his company was waiting to receive reimbursement from the El Paso County Board of Commissioners (EPBOCC) for the Loop’s first-quarter expenses. A reimbursement request for second-quarter expenses had been submitted to the EPBOCC. The Loop had spent 9% of its budget for 2025, Fromm said. Fromm told the board he expected to have a draft of the 2026 budget ready by Oct. 15.
Workshop meetings discontinued
Shaffer asked the board if the monthly work sessions were still needed. Assistant Secretary Dan LaFontaine said there were too many meetings, and some regularly scheduled meetings were less effective because the attendees from the consulting and engineering companies varied from meeting to meeting. The board decided to discontinue the meetings.
**********
The next regular meeting is scheduled for Oct. 16 at 9 a.m. Regular meetings are held on the third Thursday of each month at 9 a.m. at the Monument Town Hall at 645 Beacon Lite Road. Please see loopwater.org or call 719-488-3603 to verify meeting times and locations.
James Howald can be reached at jameshowald@ocn.me.
Other Loop articles
- El Paso County Regional Loop Water Authority, Jan. 15 – Board hears updates from Merrick and SpencerFane (2/4/2026)
- El Paso County Regional Loop Water Authority, Dec.18 – Board considers hiring executive director (12/31/2025)
- El Paso County Regional Loop Water Authority, Nov.20 – 2025 budget reviewed; 2026 budget adopted (12/4/2025)
- El Paso County Regional Loop Water Authority, Oct. 15 – Board of County Commissioners slow to reimburse (10/30/2025)
- El Paso County Regional Loop Water Authority, Aug. 28 – Board considers public-private partnership financing (9/4/2025)
- El Paso County Regional Loop Water Authority, July 17 – 2024 finances receive clean audit opinion (7/31/2025)
- El Paso County Regional Loop Water Authority, June 26 – Board hears progress report (7/3/2025)
- El Paso County Regional Loop Water Authority, May 15 – Board officers elected (6/7/2025)
- El Paso County Regional Loop Water Authority, April 17 – Pumps and pipeline proposal out for bids (5/3/2025)
- El Paso County Regional Loop Water Authority, March 20 – Contract awarded for water treatment plant design and pilot test (4/5/2025)

Leave a Comment